UN. ENGINEEMR'S OFFICE

 

Status of Projects Implemented

 

For Calendar Year 2016

 

As of June 15, 2016

 

 

 

 

Name of Project

Location

Cost/Approved Budget

Source of Fund

Project

Remarks

 

 

for the Contract

Duration

 

 

 

 

 

 

 

 

 

1

Potable Water Supply (PWS) Level II

Purok 4, Pansag, Sampao

1,650,000.00

BuB & 20% Dev't. Fund

120 Cal days

On-going

 

2

Potable Water Supply (PWS) Level II

Purok 6, Sampao, Kapalong

800,000.00

BuB & 20% Dev't. Fund

120 Cal days

On-going

 

3

Potable Water System (PWS) Level II

Pag-asa, Kapalong

1,750,000.00

BuB & 20% Dev't. Fund

120 Cal days

On-going

 

4

Potable Water System (PWS) Level II

Sua-on, Kapalong

800,000.00

BuB & 20% Dev't. Fund

120 Cal. days

BuB Fund  on process

 

5

Construction of Honeycomb

Public Cemetery, Maniki,

1,285,785.00

20% Dev't. Fund-Cont.

60 Cal. Days

On-going

 

 

 

   Kapalong

 

Appro.

 

 

 

6

Completion of Training Pool (Addt'l. Fund)

Maniki, Kapalong

800,000.00

Cont. Appro.

60 Cal. days

Completed

 

7

Rehabilitation of Potable Water System

Purok 2, Semong

230,000.00

20% Dev't Fund-Cont.

90 Cal days

On-going

 

 

 

 

 

Appro.

 

 

 

8

Desilting of Drainage Canal - Maniki

Maniki

                1,500,000.00

20% Dev't. Fund

Whole year

On-going

 

9

Maintenance of Mun. Roads

Maniki

                   500,000.00

20% Dev't. Fund

Whole year

On-going

 

10

Maintenance of Brgy. Roads

All Brgys

                2,000,000.00

20% Dev't. Fund

Whole year

On-going

 

11

Completion of Evacuation Center

Tiburcia, Elem. School

1,500,000.00

20% Dev't. Fund

90 Cal days

On-going

 

12

Const. of Two Storey Brgy. Hall Bldg.

Tiburcia

1,868,000.00

Gen. Fund

120 Cal days

On-going

 

13

Completion of Evacuation Center

Langan, Gupitan

1,000,000.00

20% Dev't. Fund

60 Cal. days

On-going

 

14

Const. of MP Building (Teachers Cottage)

Langan Elem. School

428,000.00

20% Dev't. Fund

120 Cal. days

On-going

 

15

Improvement of Multi-Purpose Bldg.

Purok 1, Semong

700,000.00

20% Dev't. Fund

60 Cal days

On-going

 

16

Const. of Brgy. Site Perimeter Fence

Katipunan

500,000.00

20% Dev't. Fund

120 Cal. days

On-going

 

17

Electrification - Purok 3, Pag-asa

Purok 3, Pag-asa

1,060,000.00

Gen. Fund

45 Cal days

Completed

 

18

Road Rehabilitation

Purok 6,8,13, & 14

300,000.00

20% Dev't. Fund

60 Cal. days

On-going

 

19

Construction of Bleacher

Capungagan

338,000.00

Gen. Fund

60 Cal. days

On-going

 

20

Construction of Bleacher

Mabantao

500,000.00

Gen. Fund

60 Cal. days

For Bidding

 

 

 

 

 

 

 

 

 

 

Sub total

 

19,509,785.00